If 6 men can dig a trench in 10 days, how many men are needed to dig it in 4 days?A15CORRECTB24C20D12
AIToaster TeacherWhy the answer is A, and why the others tempt you.The job takes 6 x 10 = 60 man-days. To finish in 4 days you need 60 ÷ 4 = 15 men.Want this in Pidgin, Yoruba, Igbo or Hausa? Sign up free →