Common EntranceMathematicsInverse Proportion

If 6 men can dig a trench in 10 days, how many men are needed to dig it in 4 days?

A15CORRECT
B24
C20
D12
AI
Toaster Teacher
Why the answer is A, and why the others tempt you.
The job takes 6 x 10 = 60 man-days. To finish in 4 days you need 60 ÷ 4 = 15 men.