Chukwuma contracted to supply 1,000 bags of cement to Danladi on July 30. On July 10, Chukwuma explicitly informed Danladi that he would not deliver the cement on the agreed date. Which of the following correctly states Danladi's legal remedies for anticipatory breach under Nigerian Contract Law?
ADanladi must wait until July 30 before initiating any legal action or treating the contract as repudiated
BDanladi may immediately accept the repudiation and sue for damages, or treat the contract as subsisting until July 30CORRECT
CThe contract is automatically discharged on July 10 without any election required by Danladi